Road Work Updates

Special Notices


We will try to keep this site up to date and accurate as possible. Changes to the schedules may occur without notice. Please try to avoid these areas during construction or plan on delays when navigating through the work zones. Paving dates are subject to change due to weather conditions.

Current Construction Schedule

 Roadway  Activities and Duration
Columba Street  A full depth reconstruction of Columba Street from Laurel Street to Ward Street, including both intersections, is scheduled to begin September 20, 2021 and will be completed in the Spring/Summer of 2022.
Crack Seal Program A program to seal cracks in road pavement is scheduled to begin on August 25, 2021. This project will conclude this construction season. Portions of the following roads are included in this project: Sheridan Street, Westover Road, Grattan Street, Broadway Street, Burnett Road, and Beauchamp Terrace.  
Fuller Road

This project has begun with completion date of August 2023.  Utility work is currently underway.  Traffic delays should be expected throughout the duration of this project.  Lane manipulation with traffic barrels / cones will be ongoing this year for utility work along Fuller Road, Sheridan Street and the Veteran’s Memorial Bridge.

The contractor, Baltazar Contractors, INC. will be working nights for one week starting this upcoming weekend. This will occur at the Fuller Rd / Sheridan St intersection to avoid traffic issues while a new water main is being connected. The night work is approved from 7:00PM to 5:00AM from Sunday, August 22nd to Thursday, August 26th, inclusive

Massachusetts Turnpike (I90)  The MassDOT will begin a project in May 2021 to realign the entrance and exit ramps at (former) Exit 6 and involves work along Burnett Road / I291 and the ramp to Fuller Road.  (This is a MassDOT project.)


Installation of driveway aprons and sidewalks scheduled for the week of 5/23/16
Installation of water main scheduled for 7/27- 8/5/16
Installation of water main scheduled for 7/27- 8/5/16
Reclamation and grading of roadway 8/2- 8/12
Reclamation and grading of roadway 8/2- 8/12
Reclaim/remove asphalt 9/6- 9/8
Fine grading 5/29- 6/4
Paving 6/4- 6/6
Fine grading 5/29- 6/4
Paving 6/4- 6/6
Grading of roadway 9/4- 9/14

Grading of roadway 9/4- 9/14
Fine grading 3/4- 3/5
Installation of dense grade gravel 3/8
Paving 3/9
Adjustment of structures 4/8- 4/11
Reclaim of roadway 4/12- 4/15
Driveways, sidewalks 6/3- 6/14
Paving 6/4- 6/5
Driveways, sidewalks 6/10- 6/21
Paving 6/10- 6/11
Driveways, sidewalks 6/24- 7/12
No construction week of 7/1
- Structure adjustment 3/27
- Sprinkler repair scheduled for Saturday April 6th
- Structure adjustment 3/27
- Sprinkler repair scheduled for Saturday April 6th